How to calculate a building job
An extension isn't a big plumbing job — it's weeks of interleaved costs that blur together. Stage-by-stage costing is how builders price builds without guessing.
Small jobs cost in one lump — an afternoon's labour and a bag of bits. A building job costs in layers spread over weeks, and by the end nobody can say what it truly cost without reconstructing it from receipts. The fix is calculating in stages, the same way the build actually happens.
Break the build into stages
Split the job the way the work runs: strip-out, groundworks and structure, first fix, second fix, finishes, external works. Each stage gets its own labour estimate, materials list, plant and subcontractor costs. Staged costing has a second payoff — it turns into your programme, your delivery schedule and your stage-invoice plan almost for free.
Cost labour across the gang honestly
Building jobs rarely have one worker. Cost each person per stage — you for five days on the structure, the groundworker for three on the footings, the chippy for a week of first fix — each at their real daily cost. Include your own time at a rate you'd pay someone else, or the “profit” is partly just your unpaid wages. And be honest about gaps: days where the brickies have finished and the plasterer hasn't started still cost the business.
Materials with real lead times and waste
Price materials stage by stage from current supplier lists — timber, blocks, insulation, plasterboard each carry a waste allowance, and the longer the build runs, the more prices can move between quoting and buying. Note lead times on the lines that matter: the steel, the windows, the doors. A priced material list that ignores lead times produces a schedule the deliveries won't keep.
Contingency for what you can't see
Foundations, drains, the state of what you're building onto — the ground gets a vote. Handle it the same way as any unknown: state the assumption in the quote, and either carry a visible contingency or agree explicitly that surprises are priced as variations before the work proceeds. “We'll sort it out when we get there” is how builders end up paying for someone else's house problems.
Overheads and profit across weeks
A six-week build carries six weeks of insurance, vehicle, scaffold hire standing time and phone. Long jobs must carry their overhead share in the price, or the quote only looks profitable because the costs arrive later than the work. Then add profit as a margin on the selling price — and check the price that margin produces against the local market before you send it.
Fixed price or estimate plus variations
Decide the contract shape deliberately. Fixed price suits builds where the scope is genuinely known — and means every overrun is yours, which makes the costing above non-negotiable. Estimate-plus-variation suits jobs with real unknowns — provided every variation is priced, approved by the customer in writing and charged. What wrecks builders is the hybrid nobody chose: a “fixed” price built on optimistic numbers, argued over at the end.
Track actuals stage by stage
As the build runs, record what each stage truly costs — hours per worker, materials as they land, variations as they're agreed — and compare against the stage estimate while the next stage can still be adjusted. That's the whole discipline, and it's the difference between finishing a build richer or just busier. Jabaro runs exactly this: stage costs against the quote across weeks of work, with live warnings when a build starts drifting toward its budget edge — and the completed build's real numbers feeding the next quote.